We contracted with Summertown Metals to build a shop building... 30x50 with 14ft walls, and later added a 12ft wide open side shed (lean-to). The plan was to have enough room inside to park an RV up to 35 foot long.
Specs: Two rollup doors (10x10 and 12x12) plus a man door. Concrete floor. Steel trusses to allow maximum interior space.

Finished build:

The framing went quick until it didn't. The material for the side shed wasn't delivered at all before the crew showed up, so they did the work they could with the materials available, and then things ground to a halt for two days until the hot-shot shipment with the additional trusses and metal showed up. That work felt a bit rushed compared to the first two days.
Concrete was installed two weeks later. Good thing we got the 12x12 door....

Specs: Two rollup doors (10x10 and 12x12) plus a man door. Concrete floor. Steel trusses to allow maximum interior space.
Finished build:
The framing went quick until it didn't. The material for the side shed wasn't delivered at all before the crew showed up, so they did the work they could with the materials available, and then things ground to a halt for two days until the hot-shot shipment with the additional trusses and metal showed up. That work felt a bit rushed compared to the first two days.
Concrete was installed two weeks later. Good thing we got the 12x12 door....
Comment